Having learned about bottlenecks, you are going through all the processes in your company to identify them and improve them. This is the analysis of the third process you are addressing:

Step 1: Capacity = 10 products in 5.15 minutes

Step 2: Capacity = 10 products in 4.67 minutes

Step 3: Capacity = 10 products in 4.75 minutes

Step 4: Capacity = 10 products in 5.25 minutes

Step 5: Capacity = 10 products in 5.33 minutes

 

Given this data, what is the best action to take for this process?